City, Howard Hughes Headed For Trial After Supreme Court Ruling Kevin Fujii/Civil Beat/2023

City, Howard Hughes Headed For Trial After Supreme Court Ruling

In a costly condemnation suit, the decision from the state’s highest court reversed a key lower court ruling that strongly favored the city and HART.

Honolulu Businesses Hurt By Rail Construction Could Get Relief But Hurdles Remain David Croxford/Civil Beat/2024

Honolulu Businesses Hurt By Rail Construction Could Get Relief But Hurdles Remain

The City Council approved an effort to jump-start an existing fund, but it’s unclear where the money will come from.

HART Board Members Question Whether Track Defects Fall Under ‘Routine Maintenance’ Kevin Fujii/Civil Beat/2023

HART Board Members Question Whether Track Defects Fall Under ‘Routine Maintenance’

City officials tried to play down the recent flaking and spalling along the train tracks. That only prompted more questions.

‘Defects’ Have Already Been Found Along Honolulu Skyline’s Tracks Cory Lum/Civil Beat/2021

‘Defects’ Have Already Been Found Along Honolulu Skyline’s Tracks

The damage was fixed but rail experts say it is “still a serious concern” and could indicate long-term issues.

HART Reaches Nearly $60 Million Settlement With Rail Contractor STG Cory Lum/Civil Beat

HART Reaches Nearly $60 Million Settlement With Rail Contractor STG

The suit had sought at least $99 million from HART. Agency leaders say the agreement won’t impact rail’s overall price tag.

HART Board Approves New Financing Deal For Rail Kevin Fujii/Civil Beat/2023

HART Board Approves New Financing Deal For Rail

The agreement, which still needs City Council approval, would pave the way for the feds to provide another $125 million for further Skyline construction.

Honolulu, Feds Reach Draft Deal To Help Fund The Rail Project Kevin Fujii/Civil Beat/2023

Honolulu, Feds Reach Draft Deal To Help Fund The Rail Project

Under the agreement, the federal government would contribute slightly more than 17% of the cost of the rail line from Kapolei to downtown.

‘High Likelihood’ Of More Delays In Critically Important Honolulu Rail Work Kevin Fujii/Civil Beat/2023

‘High Likelihood’ Of More Delays In Critically Important Honolulu Rail Work

Relocating utilities along Dillingham Boulevard has been a complex problem from the start. The HART board is asking probing questions about the schedule.

Passenger Screen Gate Alarm Triggered Skyline Train To Stall, City Says Kevin Fujii/Civil Beat/2023

Passenger Screen Gate Alarm Triggered Skyline Train To Stall, City Says

Because the train stopped at a track crossing, other trains weren’t able to get around it.

Stalled Train Temporarily Halts Service Along Skyline Kevin Fujii/Civil Beat/2023

Stalled Train Temporarily Halts Service Along Skyline

No passengers were on board that driverless train, city officials say. They haven’t said what may have stalled it.